Working Group · CMS 2026
Weekly reports
Progress reports by week from the Working Group start (18 Sep 2026) through the current week. Formal PDF/HTML packs begin 3 Oct; earlier weeks are reconstructed from repository history and SDD baselines.
Accumulated progress (W01–W04)
Headline composite at end of W04: average of Platform readiness and FE Demo depth. Checklist Live stays at 0% until durable CMS-backed journeys pass acceptance (Demo ≠ Live).
Week contributions to overall: W01 +23 · W02 +15 · W03 +8 · W04 +8 = ~54% accumulated. Method matches Overview · Project progress cuts (18 Sep → 7 Oct engineering; W04 pack refreshed morning 10 Oct).
By week — summary & cumulative %
Week 1 · 18–19 Sep 2026
Platform ~15% · FE Demo ~31% · Live 0%
Kickoff and baseline inventory. Architecture / ADR context open; student Demo/Partial already on the sheet (~31% FE). No Live checklist rows.
Reconstructed
Week 2 · 20–26 Sep 2026
Platform ~45% · FE Demo ~31% · Live 0%
Shared design-system and portal shells landed; Portal API split; Applicant shell started. Platform jumps on schema/API work; FE sheet still flat at 31%.
Reconstructed
Week 3 · 27 Sep–3 Oct 2026
Platform ~60% · FE Demo ~31% · Live 0%
Lesotho confirmed as first pilot; Demo host live; docs/campus baselines deepen. Platform ~60%; FE still sheet-flat; Live still 0%.
Baseline pack
Week 4 · 4–10 Oct 2026
Platform ~72% · FE Demo ~36% · Live 0%
Morning 10 Oct cut: hosted Applicant/Student Demo on Portal API; fee/finance YAML + cross-campus amounts; Weekly reports hub. Live still 0%.
Current week
Accumulation table
| Week | Summary | Added | Cumulative overall |
|---|---|---|---|
| W01 18–19 September 2026 |
Kickoff and baseline inventory. Architecture / ADR context open; student Demo/Partial already on the sheet (~31% FE). No Live checklist rows. | +23 pts |
~23%
P ~15% · FE ~31% · Live 0%
|
| W02 20–26 September 2026 |
Shared design-system and portal shells landed; Portal API split; Applicant shell started. Platform jumps on schema/API work; FE sheet still flat at 31%. | +15 pts |
~38%
P ~45% · FE ~31% · Live 0%
|
| W03 27 September – 3 October 2026 |
Lesotho confirmed as first pilot; Demo host live; docs/campus baselines deepen. Platform ~60%; FE still sheet-flat; Live still 0%. | +8 pts |
~46%
P ~60% · FE ~31% · Live 0%
|
| W04 4–10 October 2026 |
Morning 10 Oct cut: hosted Applicant/Student Demo on Portal API; fee/finance YAML + cross-campus amounts; Weekly reports hub. Live still 0%. | +8 pts |
~54%
P ~72% · FE ~36% · Live 0%
|
| Total accumulated (end W04) | +54 pts |
~54%
Live still 0% — not included in overall average
|
|
Related packs
- Weekly progress 3 Oct (baseline PDF/HTML)
- Weekly progress 10 Oct
- Executive review 5 Oct
- Executive summary 7 Oct
- Lesotho CMS briefing 5 Oct
- E2E Demo enrol · Applicant → staged Staff desks → Student (sequence 13 Oct) — screenshots
- E2E Demo modules · Student → Bursary/Faculty → units enrolled (11 Oct) — screenshots
- E2E Demo LMS learning · Lecturer publish → Student Materials (11 Oct) — screenshots